d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs for a sales promotion. What do you tell them and why? e. What action (if any) should be taken in period 11? Why is it okay to take the action?
On hand: 35 Planning time fence: 10 Lot size: 200 Demand time fence: 2 Period 2 4 6. 7 9. 10 11 12
a. Given the following master
to promise rows:
b. A customer wants an order of 100 in period 4. What can you tell him?
c. The customer from part (b) cancels his request, but then says he wants 120 in period 5.
What do you tell him now?
d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs for a sales promotion. What do you tell them and why?
e. What action (if any) should be taken in period 11? Why is it okay to take the
action?