Bunker Hill Mining Company has two competing proposals: a processing mill and an electric shovel. Both pieces of equipment have an initial investment of $466,339. The net cash flows estimated for the two proposals are as follows: Net Cash Flow Year 1 2 $159,000 142,000 142,000 113,000 86,000 72,000 62,000 62,000 The estimated residual value of the processing mill at the end of Year 4 is $200,000. Present Value of $1 at Compound Interest 12% 15% 20% 6% 0.943 0.890 10% 0.909 0.893 0.870 0.833 0.826 0.797 0.756 0.694 0.840 0.751 0.712 0.658 0.579 0.792 0.683 0.636 0.572 0.482 0.747 0.621 0.567 0.497 0.402 0.335 0.705 0.564 0.507 0.432 0.665 0.513 0.452 0.376 0.279 0.627 0.467 0.404 0.327 0.233 0.592 0.424 0.361 0.284 0.194 0.558 0.386 0.322 0.247 0.162 3 4 5 6 7 8 Year 1 2 3 4 5 6 Processing Mill 7 8 9 10 Electric Shovel $199,000 184,000 170,000 175,000

Managerial Accounting
15th Edition
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:Carl Warren, Ph.d. Cma William B. Tayler
Chapter12: Capital Investment Analysis
Section: Chapter Questions
Problem 1CMA
icon
Related questions
Question
Net Present Value-Unequal Lives
Bunker Hill Mining Company has two competing proposals: a processing mill and an electric shovel. Both pieces of equipment have an initial investment of $466,339. The net cash flows estimated for the two proposals are as follows:
Net Cash Flow
Processing Mill
$159,000
142,000
142,000
113,000
86,000
72,000
62,000
62,000
The estimated residual value of the processing mill at the end of Year 4 is $200,000.
Present Value of $1 at Compound Interest
10%
Year
1
2
3
4
5
6
7
8
Year
1
2
3
4
5
6
7
8
9
10
6%
0.943
0.890
0.840
0.792
0.747
0.705
0.665
0.627
0.592
0.558
0.909
0.826
0.751
0.683
0.621
0.564
0.513
0.467
0.424
0.386
12%
0.893
0.797
0.712
0.636
0.567
0.507
0.452
0.404
0.361
0.322
15%
0.870
0.756
0.658
0.572
0.497
0.432
0.376
0.327
0.284
0.247
Electric Shovel
20%
0.833
0.694
$199,000
184,000
170,000
175,000
0.579
0.482
0.402
0.335
0.279
0.233
0.194
0.162
Transcribed Image Text:Net Present Value-Unequal Lives Bunker Hill Mining Company has two competing proposals: a processing mill and an electric shovel. Both pieces of equipment have an initial investment of $466,339. The net cash flows estimated for the two proposals are as follows: Net Cash Flow Processing Mill $159,000 142,000 142,000 113,000 86,000 72,000 62,000 62,000 The estimated residual value of the processing mill at the end of Year 4 is $200,000. Present Value of $1 at Compound Interest 10% Year 1 2 3 4 5 6 7 8 Year 1 2 3 4 5 6 7 8 9 10 6% 0.943 0.890 0.840 0.792 0.747 0.705 0.665 0.627 0.592 0.558 0.909 0.826 0.751 0.683 0.621 0.564 0.513 0.467 0.424 0.386 12% 0.893 0.797 0.712 0.636 0.567 0.507 0.452 0.404 0.361 0.322 15% 0.870 0.756 0.658 0.572 0.497 0.432 0.376 0.327 0.284 0.247 Electric Shovel 20% 0.833 0.694 $199,000 184,000 170,000 175,000 0.579 0.482 0.402 0.335 0.279 0.233 0.194 0.162
Determine which equipment should be favored, comparing the net present values of the two proposals and assuming a minimum rate of return of 15%. Use the present value table appearing above.
Processing Mill
Electric Shovel
EE
Present value of net cash flow total
Less amount to be invested
Net present value
Which project should be favored?
Transcribed Image Text:Determine which equipment should be favored, comparing the net present values of the two proposals and assuming a minimum rate of return of 15%. Use the present value table appearing above. Processing Mill Electric Shovel EE Present value of net cash flow total Less amount to be invested Net present value Which project should be favored?
Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Depletions and Amortizations
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage
International Financial Management
International Financial Management
Finance
ISBN:
9780357130698
Author:
Madura
Publisher:
Cengage
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT