b-1. Identify the critical path. b-2. Identify the earliest start and finish. b-3. Identify the slack for each task. c. Which of these activities should the project manager track most closely?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

114.

Duration Task Estimates A ABCDE F 2 5 1 2 3 12 Click here for the Excel Data File Req B1 b-1. Identify the critical path. b-2. Identify the earliest start and finish. Task b-3. Identify the slack for each task. c. Which of these activities should the project manager track most closely? OUM TI Complete this question by entering your answers in the tabs below. D days days day F E F E F C days days days B A Immediate Predecessors None Identify the slack for each task. Note: Leave no cells blank - be certain to enter "0" wherever required. None A B A B and D E and C C, E B, D Immediate Successors Req B2 Req B3 Req C Latest Completion Latest Start (LS) Slack

Task
A
KOUDEE
B
С
F
Duration
Estimates
2
days
5 days
1
day
2
days
3
days
12. days
Click here for the Excel Data File
b-1. Identify the critical path.
b-2. Identify the earliest start and finish.
b-3. Identify the slack for each task.
c. Which of these activities should the project manager track most closely?
Req B1
Task
F
E
Complete this question by entering your answers in the tabs below.
D
C
B
A
Immediate
Predecessors
None
A
B
A
B and D
E and C
Req B2
Immediate
Successors
None
F
E
F
C, E
B, D
Identify the slack for each task.
Note: Leave no cells blank - be certain to enter "0" wherever required.
Latest Start (LS) Slack
Req B3
Req C
Latest
Completion
DA
Transcribed Image Text:Task A KOUDEE B С F Duration Estimates 2 days 5 days 1 day 2 days 3 days 12. days Click here for the Excel Data File b-1. Identify the critical path. b-2. Identify the earliest start and finish. b-3. Identify the slack for each task. c. Which of these activities should the project manager track most closely? Req B1 Task F E Complete this question by entering your answers in the tabs below. D C B A Immediate Predecessors None A B A B and D E and C Req B2 Immediate Successors None F E F C, E B, D Identify the slack for each task. Note: Leave no cells blank - be certain to enter "0" wherever required. Latest Start (LS) Slack Req B3 Req C Latest Completion DA
Expert Solution
steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.