also determined that if there are no resource constraints, the project should be complete in 30 working days. Table Q6-1: Precedence Relations and Durations for a Nine Activity Project Activity Predecessor ID A B C D E F G H I A ABCDE с Description Site clearing Removal of trees General excavation Grading general area Excavation for trenches Table Q6-2: Resources Required and Starting Times for a Nine Activity Project Activity Workers Earliest Start Time Latest Start Time ID Required 2 2 2 2 2 2 2 2 4 F G H I Placing formwork and reinforcement for concrete Installing sewer lines Installing other utilities Pouring concrete None None A A B,C B,C D,E D,E F,G 0 0 4 4 12 12 21 21 24 0 STESENN 9 4 15 13 12 22 25 Duration (days) 4 3 8 7 9 12 2 5 6 24 Given that only four workers are available for the project, determine the shortest possible time in which you can undertake this project. Draw a Gantt chart to show how you have arrived at your final schedule.
Q: SEARCH ASK AN EXPERT CHAT MATH SOLVER Question Let's apply our knowledge from this unit to a…
A: Introduction A business process is a collection of various elements and a coordination of…
Q: Along the Western coast of India, an oil tanker has fouled 100 miles of the shoreline. Fourteen days…
A: Answer: a) 14 days have been given to the oil company. The local crew can clean 5 miles per day So,…
Q: No. of standby units 1 2 3 Component 1 Cost (Rs.) 1 2 3 Reliability 0.70 0.85 0.95 Component 2 Cost…
A: The budget constraint of 8 Rupees means that the sum of the costs of the standby units for all three…
Q: Analyze the most pressing issues in the field of risk management. Discussion How important is risk…
A: The field of risk management is constantly evolving and facing new challenges, but some of the most…
Q: The range of productivity metrics is enormous because so many companies do so many different things.…
A: 1- Productivity in a training center can be measured in a number of ways, including: Number of…
Q: activity normal_cost crash_cost normal time(day) crash_time(day) H 3150 12550 2 6 The table shows…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: Discuss the role of the Literature Review in a scholarly article. What is it? Why are writing…
A: The literature review in a scholarly article serves as a comprehensive overview of previous research…
Q: Departments Locations
A: Given Formulas:-
Q: a-b) One of the possible assignment of tasks to workstations is shown correctly in Fig. 2. The…
A: The cycle time is given as 11 mins. To find out which activity belongs to which workstation we start…
Q: What is value chain management best defined as? Management decisions that affect how quickly the…
A: The value chain improves company efficiency so that customers may buy the highest-value product for…
Q: Which features are not necessary but would be nice to have in a seminar scheduling system?
A: The goal of a seminar scheduling system is to streamline the event planning process and provide a…
Q: Why if cleanbeebabys service so great, aren't others doin it?
A: In a popular Scott Adams cartoon, Dilbert comes upon an "inebriated hillbilly" asleep and lying on…
Q: duct specifications are met by
A: In essence, process parameters are the units' quantifiable operational parameters during your…
Q: There are six workers, one at each of the six stations (A-F). They begin their workday at 8:00 a.m.…
A: Given-
Q: What kind of link is created between the different functional units by ERP?
A: ERP or Enterprise Resource Planning is a business management software that organizations use to…
Q: 2) The specification for a Lindemann’s stainless steel chimney liner requires a thickness of 7.1 mm…
A: Given- Thickness = 7.1 mm ± 0.1 mmStandard Deviation (σ) = 0.02 mmMean thickness (x¯) = 7.13 mm
Q: Company Z has the following historical sales information for one of its hydraulic pump models for…
A: Answer: Given Data : Company Z has the following historical sales information for one of its…
Q: What is the slack of activity C?
A: To find the slack of the activity we need to find the Early Start (ES), Early Finish (EF), Latest…
Q: Define marketing logistics and list the major logistics functions?
A: Marketing logistics is an important part of any successful marketing strategy. It involves the…
Q: Part of monitoring a project as well as closing a project is to assess the project team's…
A: Project monitoring is the systematic process of tracking and controlling a project's performance,…
Q: The City Commission of Nashville has decided to build a botanical garden and picnic area in the…
A: Given data is
Q: Kindly do this in excel please
A: Decision Variables: Suppose-R be the no. of regular type baseball gloves to producedC be the no. of…
Q: Why is designing a successful service operation often more difficult than a successful design of a…
A: Services and products are the backbones of any successful business. From small businesses to large…
Q: onal companies considering cultural differences when engaging in Foreign Direct Investment.
A: For developing and rising market nations, foreign direct investment (FDI) is essential. To grow,…
Q: Earned value analysis is the project management tool that is used to measure project progress. You…
A: The project life-cycle costs follow an S-curve. Initially, the cost incurred is less, then they…
Q: Is there a way to describe what a digital signature is, and how it operates in practice? To what…
A: A digital signature is an electronic method of verifying the authenticity and integrity of a…
Q: Students are required to submit a comprehensive discussion in response to the following: 1. Identify…
A: The P-O-L-C are the four functions of principles of management. They are planning, organizing,…
Q: The forecasts generated by two forecasting methods and actual sales have been collected in the…
A: Forecasting includes making expectations about what's to come. In finance, forecasting is utilized…
Q: The Exponential Moving Average is ___________________________ A.most responsive to price movements.…
A: Forecasting is a technique used to predict future outcomes on the basis of past data. Business…
Q: Time required for the fifth unit = ? hours
A: Here, given the data stated below, The time required for the third unit=20000 hours Here, the…
Q: Fast pls i will give u like for sure solve this question correctly in 5 min pls Solve the following…
A: Decision Variables: Suppose-X be the no. of snowboard to paintY be the no. of snowmobiles to paint…
Q: Q: You purchased from your friend a specific model of a machine to do a specific job that this model…
A: In legal context, this scenario can be classified under the mistake of omission. An omission mistake…
Q: hello I need help with number 13 please and I need it only in excel
A: Product Structure tree: a. Develop a master schedule for this revised plan. (Leave no cells blank -…
Q: George Kyparisis owns a company that manufactures sailboats. Actual demand for George's sailboats…
A: Given data is Year 5 annual demand = 5600
Q: o what extent do you think an organization’s strategic plan Is influenced by the vision, leadership,…
A: A vision and mission statement is an important part of any organization. It provides a framework for…
Q: How do you quantify the most important steps in the supply chain?
A: To explain: The method the most important steps in supply chain. Concept used: Supply chain: To…
Q: Recount the value of system administration as it pertains to the operations of a business or other…
A: ANSWER : System administration is a critical function in the operations of a business or other…
Q: What happens to availability when the MTTR (mean time between failures) decreases to zero? Is there…
A: When the MTTR (mean time between failures) decreases to zero, it means that the system has become…
Q: Assign the 4 departments in Table X to locations A, B, C, and D, which are separated by the…
A: Given Formulas:-
Q: Rane Brake Linings gathered information for its brake lining components as presented in the table…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: Which approach to ethical decision making is closest to the thinking of the legal domain because it…
A: Utilitarian approach : The Utilitarian Approach evaluates a course of action in terms of its…
Q: Assume that the normal duration of activity A is 20 days and that it can be shortened to 14 for an…
A: The crash cost of finishing any work is more than the typical cost. The cost of finishing work is…
Q: Fill up the table attached. b. Compute the total transportation cost if the cost to move one…
A: Here, we could see the table related to the distance between two locations and the table related to…
Q: Explain what Sequential Quadratic Programming is, how it works, and when it's most useful for…
A: Sequential Quadratic Programming (SQP) is an optimization technique used to solve nonlinear…
Q: QUESTION 2: The Advanced Tech Company has a project to design an integrated information database for…
A: Path Duration Is duration maximum critical A-C-E-F 6+3+6+2 = 17 yes yes B-C-E-F 4+3+6+2 = 15 no…
Q: Consider the following: Activity ABCO с Normal time D 4 9 4 A E с What is the project's completion…
A: The PERT approach states that a project's completion time is normally distributed, with something…
Q: The production planner for a private label soft drink maker is planning the production of two soft…
A: Profit maximization is the inclination of businesses to increase profits over the short or long term…
Q: Due to a sudden increase in students applying for civil engineering courses, the University of…
A: The University of Greenfields wants to expand its civil engineering department due to an increase in…
Q: Is it essential to carry out configuration maintenance?
A: A configuration is a group of characteristics that designates a finished product or deliverable.…
Q: After plotting demand for four periods, an emergency room manager has concluded that a…
A: Trend adjusted Exponential smoothing -TAFt = St + TtWhere -St = Smoothed forecast = TAFt + α At -…
Step by step
Solved in 3 steps with 5 images
- 2. The following figure demonstrate the personnel involved in any project from sampling to data user. Discuss the hierarchy and role of each personnel. Project manager Sampling - Field personnel - Field engineer - Geologist Soil specialist Data user Lab analysis - Chemist Data analysis Statistician Client Decision maker QA/QC specialistCompany: ABC Civil Engineering - an engineering firmSituation: ABC company has recently made significant cuts in staff and the workload on existingemployees has increased. A major RFP is dueCharacters: Ted Waltz – Managing Director of ABC EngineeringElaine Tillman – Civil Engineer____________________________Elaine Tillman looked at her watch – it was 7:30 pm. Just then she knew she would not make it to her son’s final high school basketball game. It took her a moment to collect herself and wipe the tear that had started down her face and onto the ragged-edged 100 plus page RFP she was working on. The RFP,the largest opportunity that ABC Civil Engineering had a chance to bid on in 6 months, was far fromready for the 9:00 AM deadline the following day.Normally in this situation, Elaine would have collaborated with a proposal team putting together such a big proposal but, since the economic down turn hit, ABC has had to make significant cuts in its staff. It started with administrative…Company: ABC Civil Engineering - an engineering firmSituation: ABC company has recently made significant cuts in staff and the workload on existingemployees has increased. A major RFP is dueCharacters: Ted Waltz – Managing Director of ABC EngineeringElaine Tillman – Civil Engineer____________________________Elaine Tillman looked at her watch – it was 7:30 pm. Just then she knew she would not make it to her son’s final high school basketball game. It took her a moment to collect herself and wipe the tear that had started down her face and onto the ragged-edged 100 plus page RFP she was working on. The RFP,the largest opportunity that ABC Civil Engineering had a chance to bid on in 6 months, was far fromready for the 9:00 AM deadline the following day.Normally in this situation, Elaine would have collaborated with a proposal team putting together such a big proposal but, since the economic down turn hit, ABC has had to make significant cuts in its staff. It started with administrative…
- A company that makes food-friendly silicone (for use in cooking and baking pan coatings)is considering four independent projects shown, all of which can be considered to be viable for only 10 years. The company's MARR is 15% per year. Project A B C D First Cost, $ -1500 -2300 -5600 -7600 Annual net Income, $/year 200 460 1150 1200 Salvage value, $ 5 6 8 7 Determine which products to implement Financial values are in $1000 units. The present worth of project A is $___________, So project A is ___________(Rejected / Accepted) The present worth of project B is $___________, So project B is ___________(Rejected / Accepted) The present worth of project C is $___________, So project C is ___________(Rejected / Accepted) The present worth of project D is $___________, So project D is ___________(Rejected / Accepted)What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL TIME (DAYS) CRASH TIME (DAYS) 5 4 ACTIVITY Design (A) Wiring (8) Chip install (C) 7 5 3 4 7 2 2 4 NORMAL COST 300 900 500 CRASH COST 1,100 1,200 350 975 575 Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $1,875 (enter your response as a whole number). IMMEDIATE PREDECESSOR(S) 1,300 1,650 A, B сMASTERY PROBLEM / Cr. Cash: $4,301.83 ar Ban Trenkamp owns and operates the Trenkamp Collection Agency. Listed below are the name, number of allowances claimed, marital status, information from time cards on hours worked each day, and the hourly rate of each employee. All hours worked in excess of 40 hours for Monday through Friday are paid at 1½ times the regular rate. All weekend hours are paid at double the regular rate. Trenkamp uses a weekly federal income tax withholding table (see Figure 8-4 on pages 288 and 289). Social Security tax is withheld at the rate of 6.2% for the first $110,100 earned. Medicare tax is withheld at 1.45% and state income tax at 3.5%. Each employee has $5 withheld for health insurance, All employees use payroll deduc- tion to the credit union for varying amounts as listed. GENERAL LEDGER Trenkamp Collection Agency Payroll Information for the Week Ended November 18, 20-- Credit Total Hourly Rate Earnings 1/1-11/11 Union Employee No. No of Allow. Regular…
- 1. Decision Rules. A company is choosing a motorized mechanism for a new toy, a dancing ballerina (TippiToes) that is currently under development. Demand is uncertain. but the company is confident that demand will be: Light (25,000 units), Moderate (100,000 units) or Heavy (150,000) units. The payoff table for each mechanism (in $) is given below. Action: Choice of Mechanism Event Gears and Levers Spring Weights and Pulleys Pneumatic Light 25,000 -10,000 -125,000 -300,000 Moderate 400,000 440,000 400,000 300,000 Heavy 650,000 740,000 750,000 700,000 Questions: (1) Apply Maximax, Maximin, Minimax Regret, and EMV rules (assuming that the probability of Light demand is 0.1, Moderate demand is 0.7, and Heavy demand is 0.2) to decide what mechanism should the company choose? (2) What is the expected value of perfect information? (3) Draw a decision tree to solve this problem.Give a generaldescription of PERT/CPMtechniques.A B с D E FL ד G H J K L M N P R S T U V 1 On Week 3 Forecast 4 2 a) Smell Fresh Customer Orders hand 1 2 20 20 5 3 5 PAB 20 50 30 3222 4 5 6 7 8 Problem 6: Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Partially-completed MPS time-phased record is given below. 20 30 30 30 30 30 Week 10 30 50 20 40 10 Item: Smell Fresh On hand 1 6 Available to Promise 7 MPS 50 50 50 50 Forecast 20 8 MPS lot size = 50 9 20 10 On Week hand 2 3 4 5 6 7 8 9 20 53 43 78 30 30 30 30 30 3220 2233 -250 30 10 30 50 6 8 45 12 13 14 PAB 15 11 b) Smell Fresh Forecast Customer Orders Available to Promise 16 MPS 17 MPS lot size=50 18 19 20 21 23 24 222 Orders Projected available balance Available-to-promise MPS MPS Lot Size = 50. 50 20 40 10 50 50 50 a) Complete the MPS time-phased record (the first table on the left). The following events occurred during week 1: • Actual demand during week 1 was 25 units. • Marketing forecasted that 40 units would be needed for…
- BSOP 588 Managing QualityAll Assignments Course Projects, Midterm and Final ExamWeek 2 Course Project:BSOP 588 Week 2 Project Proposal (Toyota Motor Corporation)Week 3 Assignments:Week 3 Paper; Measuring Customer Service – MCS (Jan 2013)Week 3 Paper; Measuring Customer Satisfaction (July 2014)Week 4 Midterm ExamSET 1Page 1Question (TCO A) Compare and contrast the evolution of quality and the role it played in the management of U.S. and Japanese business firms from the 1950s to the present.Question (TCO B) Compare and contrast the following definitions of quality. Definition 1: Quality is the totality of features and characteristics of a product or service that bears on its ability to satisfy given needs. Definition 2: Quality is meeting or exceeding customer expectations.Question (TCO A) Explain the three core principles of total quality.Question (TCO H) Identify and discuss five differences between service and manufacturing organizations.Question (TCO B) Cite two ways that the…“To cut the number of projects, the steering committee used a weighting scheme that reflected theairline’s priorities, which were: fly safe, generate revenue, reduce costs, and customer service. Theweighting scheme easily weeded out the fluff.”Use a weighted scoring model to help the committee choose between two projects: Booking SystemUpgrade and Cabin Crew Retraining. The relative weights for each criterion and the assessment ofeach project for these criteria are shown in the following table. Which project would you choose andwhy? (See extract attached to assist) (Assume 10 represents the preferred score and 1 represents the undesired score.) Criteria Weight Booking System Upgrade Pilot Crew Retraining Fly safe 40 4 10 Generate revenue 30 9 9 Reduce costs 20 7 8 Customer service 10 10 10“To cut the number of projects, the steering committee used a weighting scheme that reflected theairline’s priorities, which were: fly safe, generate revenue, reduce costs, and customer service. Theweighting scheme easily weeded out the fluff.”Use a weighted scoring model to help the committee choose between two projects: Booking SystemUpgrade and Cabin Crew Retraining. The relative weights for each criterion and the assessment ofeach project for these criteria are shown in the following table. Which project would you choose andwhy? (See extract attached to assist) (Assume 10 represents the preferred score and 1 represents the undesired score.) Criteria Weight Booking System Upgrade Pilot Crew Retraining Fly safe 40 4 10 Generate revenue 30 9 9 Reduce costs 20 7 8 Customer service 10 10 10 Use the Template in the attached