Ahead of schedule Behind schedule a. The status of the project in terms of schedule: Under budget Over budget b. The status of the project in terms of cost:

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
25: a) The scheduled work activities for a project, together with the corresponding
duration and budgeted amount estimated at the start of the project, are shown in the
table below. In a weekly progress meeting at the end of the 42nd day of the project,
the contractor reports that the paving has been placed and is ready for application of
the sealer. The contractor also explains that new compacting methods have helped
reduce the project costs by $3.000 below the total budgeted cost for construction
through placement of the paving. Determine the following using Earned Value
Ahead of schedule
Behind schedule
a. The status of the project in terms of schedule:
Under budget
Over budget
b. The status of the project in terms of cost:
Original
Budget
Duration
Work Item
(working days)
Mobilize to site
$2,000
Demolish old parking lot
3.
$15,500
Excavation and sitework
$12,500
New underground utilities
Compacted sub-base
Concrete walkways and planters
12
$23,000
4.
$9,500
10
$18,500
Paving
6.
$22,500
Pavement sealer
$6,500
Striping
$4,000
Lighting
Landscaping
$7,500
$5,500
Final Clean-up, De-mobilize
$2,000
Total
51
$129,000
323
Transcribed Image Text:25: a) The scheduled work activities for a project, together with the corresponding duration and budgeted amount estimated at the start of the project, are shown in the table below. In a weekly progress meeting at the end of the 42nd day of the project, the contractor reports that the paving has been placed and is ready for application of the sealer. The contractor also explains that new compacting methods have helped reduce the project costs by $3.000 below the total budgeted cost for construction through placement of the paving. Determine the following using Earned Value Ahead of schedule Behind schedule a. The status of the project in terms of schedule: Under budget Over budget b. The status of the project in terms of cost: Original Budget Duration Work Item (working days) Mobilize to site $2,000 Demolish old parking lot 3. $15,500 Excavation and sitework $12,500 New underground utilities Compacted sub-base Concrete walkways and planters 12 $23,000 4. $9,500 10 $18,500 Paving 6. $22,500 Pavement sealer $6,500 Striping $4,000 Lighting Landscaping $7,500 $5,500 Final Clean-up, De-mobilize $2,000 Total 51 $129,000 323
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.