a. Determine a sequence that will minimize makespan time.
Q: Job 1 4 7 8 Processing Time 9 5 4 5 3 Due Date 4 21 22 12 13 12 34 36 Processing time and due date…
A:
Q: Job 1 2 3 4 7 8 Processing Time 3 6. 4 5 2 3 Due Date 4 21 22 12 13 12 34 36 Processing time and due…
A: Utilize the SPT calculation. By and large, among all the heuristics, SPT will limit the normal…
Q: Case 1 In this case there are five Jobs Stage-1 1,5 1,25 1,75 1,25 1,5 Stage-2 jobs that each must…
A: Here, unit of time is not given. So for a understanding, we have taken it as minutes. It wont matter…
Q: Raquel is concerned with effi ciency. She believes it isprobably more effi cient to use SPT…
A: SPT based processing time can be depicted as follows:
Q: Which are the Principles of Workcenter Scheduling?
A: Work center scheduling is the process of allocation of all the resources of an organization to…
Q: 77 During the execution of a project, it is discovered that not all work packages included the…
A: Project Execution is the stage of the project life cycle in which the work is completed and the…
Q: Which Priority Rules are used for Job Sequencing?
A: Job scheduling is an important aspect of the production process. Jobs that are sequenced properly…
Q: Relative to job-based scheduling, how does a finite load differ from an infinite load?
A: Employees are scheduled to perform work based on their job code which means labour standards are…
Q: Five jobs must be scheduled for batch processing on a mainframe computer system. The processing…
A:
Q: Using the critical ratio scheduling rule, in what sequence would the jobs to process?
A: The critical ratio (CR) is is a tool to set priority sequencing of work that is waiting for the…
Q: Seven jobs are to be processed through a single machine. The processing times and due dates are…
A: A:Sequencing decide that determines that the occupation requiring the most limited handling time is…
Q: Does the law allow a rest day to fall on a “Wednesday”?
A: In the above case it is mentioned that Jose was directed by his superior for extending his work hour…
Q: An anticipated result from multi programming operations is: a. better scheduling of work b. the…
A: Sharing the processor, when two or more programs reside in memory at the same time, is referred as…
Q: Consider the following single machine-scheduling problem with weights: Job G) A B D E F G Processing…
A: As per SPT rule, we will arrange processing time in ascending order. Using the SPT rule, the…
Q: snip
A: Given, Oscar: 2 weeks of work and due in 4 weeks. Lima: 3 weeks of work and due in 5 weeks. Denver:…
Q: 2IA Five tasks to be completed in three places A, B and C and the work sequence is A and then C, B…
A: Find solution of Processing 3 Jobs Through 5 Machines Problem Job A B C Machine-1 4…
Q: A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the…
A: A project consists of a group of specialized and skilled workers working together for a common…
Q: a) Using the FCFS (first come, first served ) decision The following jobs are waiting to be…
A: In FCFS (First come, First served) decision method for arranging the tasks, the order is the…
Q: JOB JOB TIME (HOURS) DUE DATE (HOURS) A 12 15 B 6 24 C 14 20 D 3 8 E 7 6 Determine the processing…
A: Process sequencing is a process to process the order in the sequence that it is received.There are…
Q: A group of 6 jobs is to be processed through a 2-step operation. The 1st involves cleaning and the…
A: Sequencing is an appropriate order of plan as per which the process of operations works. It defines…
Q: d) Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to…
A: LPT rule: Sequence Job 1 E 2 D 3 C 4 A 5 B
Q: A key part of work center scheduling is job sequencing—deciding in what order jobs are scheduled to…
A: “Priority rules” is the term for the simple rules which is a key part of work center scheduling.…
Q: le to those of Shorte
A: The priority scheduling algorithm works on the processes on the basis of their priority. To ensure…
Q: Give examples of unethical behaviour involving scheduling in the organisation
A: Scheduling relates to the procedure of controlling, organising and optimising the workload in the…
Q: What do Priority Scheduling and Shortest Job First Scheduling have in common?
A: Priority scheduling executes the progressions liable upon their priority. Respectively process is…
Q: 1. What is the cycle time? 2. What is the theoretical minimum number of workstations? 3. Which of…
A: Cycle time is the actual and total time incurred to manufacture a particular item of the product in…
Q: Given the following information on job times and due dates. Job Job Time (Hours) Due Date (Hours)…
A: we'll answer the first question since the exact one wasn't specified. please submit a new question…
Q: Job 1 3 4 7 8 Processing Time 3 9. 4 2 Due Date 4 21 22 12 13 12 34 36 Processing time and due date…
A:
Q: At the campus copy shop, six jobs have a rrived in the order shown (A, B, C, D, E, and F) at the…
A: As per the Bartelby guidelines only the first three parts have been answered: The jobs given have…
Q: Seven jobs are to be processed through a single machine. The processing times anddue dates are given…
A: The performance as per FCFS, SPT, EDD, CR, MOORES algorithm are as follows :
Q: Qus 1: Find the FCFS Schedule? Qus 2: Find the SOT Schedule? Qus 3:Find the DDate Schedule? Qus…
A: The job scheduling process is a time-consuming and complicated task. It requires a lot of time and…
Q: snip
A: Johnson's rule is one of the rules in the schedule that tries to prioritize tasks or jobs in a…
Q: The late start time for an activity is equal to the late finish time minus the activity time. True…
A: The answer is True.
Q: 3. The table below shows the ready time, process time and due date of 7 jobs. Job ID Ready Time…
A: Given data is
Q: iven we apply the most aining the tasks that will be assigned to the SECOND workstation are
A: Answer is
Q: Date Determine the sequence to minimize the sum of Earliness and Tadiness Job sequence: 3
A: The answer is as below:
Q: 24 The job that arrived first at a work center or machine will be processed first and completed.…
A: One of the definitive objectives in assembling is to guarantee that all client requests are…
Q: Jobs A, B, C, D, and E must go through Processes I and II in that sequence (Process Ii rst, then…
A:
Q: snip
A: The scheduling of these three jobs as per the shortest processing time (SPT) will lead to the…
Q: 4a. Use examples to explain how resource scheduling can reduce the flexibility in managing projects?
A: Resource scheduling is an inventory measurement that is used to schedule the inventory so that the…
Q: Ron Satter field's excavation company uses bothGantt scheduling charts and Gantt load charts.a)…
A: A Gantt chart refers to a management tool used to visualize a project to help in its planning and…
Q: CREATE A GANTT CHART USING THESE SCHEDULED TASK:
A: Task Start End Excavation 2/23/2022 2/23/2022 Backfill 3/7/2022 3/11/2022 Reinforcing…
Q: Which statement is correct? O a. There could be more than one critical path in a network of…
A: Even if each task is important, just a few are critical. The critical route is a set of…
Q: What happens if there are a large number of tasks with the same priority?
A: Realizing how to focus on work influences the achievement of your undertaking, the commitment of…
Q: a) Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is…
A: In the FCFS (first come, first served) rule jobs are arranged through their arrival times.…
Q: In problem 3, assume there are two machines of type A, two of type B, and two of type C. a. Prepare…
A: The Answers of question 3 are as follow:- a)the makespan is 14 hours b) machine idle time for…
Q: What are the objectives of workcenter scheduling?
A: Workcenter scheduling is the scheduling which is designed or created to meet the range of the goals…
Q: Job 1 3 4 6. 7 Processing Time 3 9. 4 2 3 Due Date 4 21 22 12 13 12 34 36 Processing time and due…
A:
Q: 14. In Muscat Machine Manufacturing company, following 6 jobs are waiting to be processed. All the…
A: Answer: Critical ratio is calculated by dividing the time left until a job's due date by total…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images
- Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job A B Processing Time (days) I5 Due Date 11 6 3 16 19 10 D E 15 Using the earliest due date (EDD) rule, the average lateness for the five jobs is decimal place. Round your answer to one Your Answer: AnswerFive customers brought in computers to be repaired to a small shop. Estimated repair times (in days) and dates promised are given below. Due dates were set based on available technicians; however, one technician had a medical emergency and will be unavailable for at least two weeks so processing times were adjusted. Customer job 1 Processing time (days) Due date (days) 6 Use the EDD rule and compute the start time, flow time, lateness, and tardiness for each job. Use minus sign to enter negative lateness values, if any. If your answer is zero, enter "0". Sequence Start Time, days Flow Time, days Lateness, days Tardiness, days -Select- -Select- -Sclect. -Select- -Select- UI 5 LI TE 10 MAThe times required to complete each of eight jobs in a two-machine flow shop are shown in thetable that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B.a. Determine a sequence that will minimize makespan time.b. Construct a chart of the resulting sequence, and find machine B’s idle time. c. For the sequence determined in part a, how much would machine B’s idle time be reduced bysplitting the last two jobs in half?TIME (hours)Job Machine A Machine Ba 16 5b 3 13c 9 6d 8 7e 2 14f 12 4g 18 14h 20 11
- The following jobs are waiting to be processed at thesame machine center. Jobs are logged as they arrive:JOB DUE DATE DURATION (DAYS)A 313 8B 312 16C 325 40D 314 5E 314 3 In what sequence would the jobs be ranked according to the follow-ing decision rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? All dates are specified as manufacturing planning calendar days. Assumethat all jobs arrive on day 275. Which decision is best and why?The following jobs are waiting to be processed at JulieMorel’s machine center:JOB DATE ORDER RECEIVED PRODUCTIONDAYS NEEDED DATE ORDER DUEA 110 20 180B 120 30 200C 122 10 175D 125 16 230E 130 18 210 In what sequence would the jobs be ranked according to the fol-lowing rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? All dates are according to shop calendar days. Today on the planning cal-endar is day 130, and none of the jobs have been started or sched-uled. Which rule is best?K Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning, and she must decide in what order to write the code. Assume that all jobs arrived today (day 1 and hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a work day. JOB A C D E DUE DATE (HOURS HENCE) 10 16 14 36 26 DURATION (HOURS REQUIRED) 6 3758 a) Sequence the jobs according to EDD. According to the EDD rule, the sequence of jobs should be A, C, B, E, D b) What is the average completion (flow) time? The average completion (flow) time is days (round your response to one decimal place).
- The following six jobs are to be scheduled on a single machine: Job 1 2 3 Processing time 70 160 220 (min.) a. Suppose the jobs are processed in FCFS numerical order. Compute the makespan, flow time for each job, and overall average flow time. Round your answers to the nearest whole number. Job Flow Time (min) 1 2 3 st 4 5 6 4 5 6 90 130 110 minutes Makespan: Average flow time: minutes b. In what order would the jobs be processed using the SPT rule? The SPT sequence is -Select- -Select- -Select-- -Select- ✓ -Select- -Select- Compute the average flow time after each job is completed. Round your answer to the nearest whole number. Average flow time: minutesThe following jobs are waiting to be processed atJulie Morel’s machine center: In what sequence would the jobs be ranked according to thefollowing rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT?All dates are according to shop calendar days. Today on theplanning calendar is day 130, and none of the jobs have beenstarted or scheduled. Which rule is best?I only need help with question 4, but question 3 explains how to do 4 but I'm lost. I already have question 3 done. 3. Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4. Job Work Center/Machine Hours Due Date (days) Job 1 A/3, B/2, C/2 Job 2 C/2, A/4 Job 3 B/6, A/1, C/3 Job 4 C/4, A/1, B/2 a. What is the makespan? b. How much machine idle time is there? c. When is each job delivered compared with its due date? d. How much idle time (waiting time) is there for each job? e. Devise a better job sequence for processing. 4. In problem 3, assume there are two machines of type A, two of type B, and two of type C. a. Prepare a finite capacity schedule. b. Compare the FCS to the Gantt chart in problem 3.
- Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning, and she must decide in what order to write the code Assume that all jobs arrived today (day 1 and hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a work day. DURATION (HOURS JOB k A BUD C E DUE DATE (HOURS HENCE) 10 16 14 36 26 REQUIRED) 6 3 7 15 8 a) Sequence the jobs according to EDD. According to the EDD rule, the sequence of jobs should be A, C, B, E, D b) What is the average completion (flow) time? The average completion (flow) time is days (round your response to one decimal place).A group of six jobs is to be processed through a two-machine flow shop. The first operation involves cleaning and the second involves painting. Determine a sequence that willminimize the total completion time for this group of jobs. Processing times are as follows:PROCESSING TIME (hours)Job Work Center 1 Work Center 2A 5 5B 4 3C 8 9D 2 7E 6 8F 12 15 To employ Johnson’s rule, create a “blank” sequence first, such as:mhhe.com/stevenson13eEXAMPLE 41st 2nd 3rd 4th 5th 6thThe following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) Job CR Job Due Date Duration (days) 103 103 214 10 205 205 223 309 309 217 11 412 219 412 517 216 15 517 Assume that all jobs arrived on day 180; today's date is 200.