A project requires an initial investment in equipment of $760,000 immediately (t=0) and is expected to produce sales revenue of $697, 000 the first year; this revenue will increase by 4.5% per year over the next four years. Manufacturing costs are estimated to be 67% of the sales. The project demand analysis, which was done last year, cost $235,000. The asset can be depreciated on a straight-line basis over five years to a zero salvage value. The corporate tax rate is 36%. The project requires an investment in working capital. Specifically, at the beginning of the project (t=0), $45,000 of working capital is required; thereafter, working capital is projected to be 6.0% of revenue. The investment in working capital will be recovered at the end of the fifth year. At the end of the 5th year, the company plans to sell the equipment for $18,900. To calculate the cost of capital for this project, the firm is going to use the following companies as comparable firms.   Beta Debt Equity XOM 1.00 11.63B 403.10B CVX 1.22 20.02B 224.24B Assume that the market risk premium is 6%, the risk free-rate is 5%, and all debt is risk free, static and perpetual, and that the CAPM holds. The firm is going to finance the project with all equity. QUESTION: Suppose the firm can expand the value of the project by 50 percent at the end of year 1 with an additional investment of $500,000. Further, the firm has the option to sell the asset to another firm at the end of year 1 for $600,000. If the returns of the project have a standard deviation of 25% and the risk-free rate is 5%, what is the value of the project including these options? Use a binomial tree with 2 steps to determine the value

EBK CONTEMPORARY FINANCIAL MANAGEMENT
14th Edition
ISBN:9781337514835
Author:MOYER
Publisher:MOYER
Chapter11: Capital Budgeting And Risk
Section: Chapter Questions
Problem 15P
icon
Related questions
icon
Concept explainers
Topic Video
Question

A project requires an initial investment in equipment of $760,000 immediately (t=0) and is expected to produce sales revenue of $697, 000 the first year; this revenue will increase by 4.5% per year over the next four years. Manufacturing costs are estimated to be 67% of the sales. The project demand analysis, which was done last year, cost $235,000. The asset can be depreciated on a straight-line basis over five years to a zero salvage value. The corporate tax rate is 36%. The project requires an investment in working capital. Specifically, at the beginning of the project (t=0), $45,000 of working capital is required; thereafter, working capital is projected to be 6.0% of revenue. The investment in working capital will be recovered at the end of the fifth year. At the end of the 5th year, the company plans to sell the equipment for $18,900.

To calculate the cost of capital for this project, the firm is going to use the following companies as comparable firms.

 

Beta

Debt

Equity

XOM

1.00

11.63B

403.10B

CVX

1.22

20.02B

224.24B

Assume that the market risk premium is 6%, the risk free-rate is 5%, and all debt is risk free, static and perpetual, and that the CAPM holds. The firm is going to finance the project with all equity.

QUESTION: Suppose the firm can expand the value of the project by 50 percent at the end of year 1 with an additional investment of $500,000. Further, the firm has the option to sell the asset to another firm at the end of year 1 for $600,000. If the returns of the project have a standard deviation of 25% and the risk-free rate is 5%, what is the value of the project including these options? Use a binomial tree with 2 steps to determine the value

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College