8-The critical path time is All options are incorrect O 8 17
Q: PM.52 HCA (Hospital Corporations of America) has obtained 5 new hospitals in a recent acquisition.…
A: Possible path Duration Maximum Critical ABDGIJK 1+5+6+14+12+2+5 = 45 No No ABEHJK 1+5+7+12+2+5…
Q: Draw the activity-on-node (AON) project networkassociated with the following activities for Carl…
A: Project scheduling is a tool used by organizations and managers in project planning and…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Note: - As we can answer only three subparts, the first three(a, b, and c) will be answered. If…
Q: 4. Calculate the late finishing time (backwards calculations) 5. Calculate the slack time of the…
A: Formula:
Q: 1. The activities involved in the construction of a certain project are given in Table 1. One…
A: Given the following activity data:
Q: I need help with chapter 17, problem 2 (17.2) Question is A-D
A: a)Arrange the activities into two logical sequences:
Q: Q 2/Draw the PERT network from the given Finformation in the table below: Activity 1 M 12 a 18 1 3…
A: Given Information:
Q: 5. Management wants to design an assembly line that will turn out 800 videotapes per day. There will…
A: Note- We’ll answer the first three subparts of the question since the exact one wasn’t specified.…
Q: a. What is the length of the critical path? Length of the critical path hours
A: Below is the solution:-
Q: Q3: What is Critical Path Analysis? Explain with the help of a suitable example.
A: In a project network with various activities and forming various paths to finish the project, the…
Q: (1) O Construct a network diagram with activity on arrow method; (1) Estimate the expected project…
A:
Q: QUESTION 2 The Human Resources Department is considering a project to upgrade its current payre…
A: Activity on Node diagram: Following format used for network diagram: Early Start(ES) Duration…
Q: Table contains information about an environmental cleanup project in the township of Hiles. Shorten…
A: Solution The minimum cost schedule is calculated by crashing those activities which has minimum…
Q: 1. The R&D department is planning to bid on a large project for the development of a new…
A: A project network is the visual representation of the project activities and their respective…
Q: 3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde…
A: 3.8) Given Activity Immediate Predecessor(s) Time(Days) A ______ 2 B ______ 5 C ______ 1…
Q: A) Draw Precedence diagram (PD). B) Calculate completion data, what is completion data. C) Identify…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 1) Find out the CP by drawing the Network diagram (need to show ES, Duration.EF, LS, LF, Slack) 2)…
A: Below is the solution:-
Q: EQUIRED: a. The PERT Network, identifying the critical path and including slack times.
A: We are only allowed to do one question at a time. Please post rest questions again to get answer.
Q: A. Instruction: 1. Construct both AOA diagram for the following data. a) b) Identify the paths and…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Table 7.8 contains data for the installation of new equipment in a manufacturing process at Excello…
A:
Q: Activity Precedence Activity Times (in week) A A 8 C В D A E C,D F E 8 E 7 H E F,G,H 4 4
A: A Gantt chart, generally employed in project management, is one of the most familiar and helpful…
Q: 9. At a local university, the Student Commission on Programming and Entertainment (SCOPE) is…
A: Note: - Since the exact that has to be answered is not specified, we will answer the first…
Q: Q2(a) Choong Machinery specializes in developing grass cutting equipment. Mr Ahmad, who is an R&D…
A: Given data, Solution: Activity Immediate Predecessors Duration A - 6 B - 5 C A 3 D A 2…
Q: Activity Times (days) Activity Cost ($) Immediate Activity Predecessor 100 None 150 None 125 А D 175…
A: given,
Q: Requirement 2. Ralph does not like the idea of sharing the costs equally because he plans to stay in…
A: Given information: Costs and Allocation Allocation B R Costs Food Eaten (in pounds) 16 34…
Q: 1: Program Evaluation Review Technique by using Activity on Arrow Method 2 Critical Path Method…
A: Below is the solution
Q: 17.6. Decenture has four new IT hires available for assignment to ERP implementation projects. Their…
A:
Q: Q.No.3. When we start a project how we know this project or program is feasible for our future?…
A: Before starting a project, its feasibility for the future is understood by the feasibility study.…
Q: Instruction: a. Construct AON diagram for the following data. b. Identify critical path c. Conduct…
A: Find the Given details below: Activity ImmediatePredecessors Time Estimates (Days) A - 2 B -…
Q: Construct a network diagram using AON notation
A: GIVEN
Q: ... 3.16 The Rover 6 is a new custom-designed sports car. An analysis of the task of building the…
A:
Q: QUESTION 9 4 Aini is a network device commonly used to display project schedules. It was developed…
A: A complete handwritten solution is provided as asked by the student. Here, please refer to step 4…
Q: II. TRUE/FALSE 1. () The critical path can be determined by use of either the "forward pass" or the…
A: Critical path is described as the set of activities that adds up and takes the maximum duration.
Q: Jamison Day Consul tants has been entrusted with thetask of evaluating a business plan that has been…
A: a) The allocation of optimal team members as per Hungarian model can be: Team member Section…
Q: Q3- Udesign is a plant producing mass production dresses. The following table shows the tasks needed…
A:
Q: 7. The project information for the custom order project of the Air Control Comp presented here. Draw…
A:
Q: Estimated Duration (days) Activity Precedes A в 15 в с, D 12 E 6 D End 5 E End 3 G, H G I J End J K…
A: The activities that have a slack of zero are known as critical activities. It is crucial to complete…
Q: 1. For cach of the following network diagrams, determine both the critical path and the expected…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 1) Draw and AOA diagram. ) Identifying due time of the critical path :) Compute for te, Path total,…
A: AS PER GUIDELINES, WE ARE ALLOWED TO DO THE FIRST THREE SUB PARTS ONLY. PLEASE POST THE REST…
Q: Find:(1) The critical path. (2) The completion time. (3) The float time.
A:
Q: Task ID Duration Dependency A 3 B 14 C.F A 2
A: Activity Immediate Predecessors Duration A - 3 B A 4 C B 3 D C,F 5 E A 6 F E 2
Q: 5. As part of a major plant renovation project, the industrial engineering department has been asked…
A: We’ll answer the first question since the exact one wasn’t specified. Please submit a new question…
Q: 14 - In earned value analysis, we found that BCWP: $24,800 BCWS: $27,650 ACWP: $21,900 The project…
A: Earned Value Analysis (EVA): It is a system that enables the project manager to estimate the amount…
Q: Q3- Udesign is a plant producing mass production dresses. The following table shows the tasks needed…
A: Given Information: Required Output = 30 dresses per hour
Q: a) Prepare the Activity Node Diagram and identify the Critical Path
A: “Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: PM.66 Real estate developer Russell Call was working with a few contractors to make a number of…
A: Given-
Q: 04 - The network diagram of one of the projects and its data as in Table No, (4), so if I want to…
A: THE ANSWER IS AS BELOW:
Q: 7. The project information for the custom order project of the Air Control Company is presented…
A: Activity and Slack TimeThe AON project network is a project network with activities being…
Step by step
Solved in 3 steps with 2 images
- Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost 1st Week 2nd Week A ― 9 $410 $415 B A 7 125 -- C A 5 45 45 D B 4 300 350 E C 6 50 -- F D, E 5 200 225 G F 8 -- -- H F 7 85 90 I G 6 90 -- Construct a network diagram for the project Indicate the critical path when normal activity times are used. Develop a crashing schedule. Note: No activity can be crashed more than two weeks. Show breakdown of workQ6:write briefly but relevant answer a) PERT and CPM b) Risk Management and its types.1 Cara's clients, Emily and Dave, have just had a baby and she would like to do something nice for them. She signs them up for a baby registry that sends them a small gift. Emily and Dave will be sent information and service lists that are geared toward helping new parents. She provided their names, address and phone numbers so that they will not miss any of the activities provided in the package. Has Cara dealt with her clients appropriately? NUYLOTNQhObm1bEVKUTO90 a0 Cara did not protect her clients' privacy when she shared their personal information with the baby registry. O Cara should not make this a regular practice. Her clients will begin to expect gifts and she will not be able to sustain this. CO Cara should have set up an appointment to re-evaluate her clients' needs now that they have had a baby. 40 Cara's gift is very thoughtful and will help to build a relationship with her clients. NUTYks10TNRUQ2h0bmkbEVKUTO90
- Image of Diagram included Using the diagram, find: The critical path. How long it will take to complete the project? How does simulation determine the probabilities of various project completion times? What is "slack" and why is it important? Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? How is the uncertainty in project scheduling dealt with? Should the critical path activities be managed differently from noncritical path activities? Explain.What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL TIME (DAYS) CRASH TIME (DAYS) 5 4 ACTIVITY Design (A) Wiring (8) Chip install (C) 7 5 3 4 7 2 2 4 NORMAL COST 300 900 500 CRASH COST 1,100 1,200 350 975 575 Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $1,875 (enter your response as a whole number). IMMEDIATE PREDECESSOR(S) 1,300 1,650 A, B сOpp l +O 90% 10:31 33,19 K/s UNIVERSITY OF GHANA 35 Part 1 of 1- Question 1 of 100 . refers to how the project is expected to work and solve the stated problem in project or proposal writing. A. Project Portfolio B. Portfolio of Activities C. Plan of Activities D. Project Activities Reset Selection [1] Question Progress
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Immediate Predecessor(s) Activity ABCDEFG This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B A, D C E, F Time (days) 4 5 3 10 4 6 10B/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4Preceding Activity Crashed Cost per week $600 $700 $400 Activity Normal Completion Time (week) Crashed Completion time (week) A 7 5 B 12 10 A 8 2 $800 $300 $500 E C, D 5 4 F E 9 8 D. F 10 10 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table, ii. Showing the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the project determine the completion time of the project and the critical path. ii. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. iv. Need proper handwritten answers. Thank you!
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity D. Activity B is connected to activity E. Activity C is connected to activity F. Activity D is…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity C. Activity B is connected to activity E. Activity C is connected to activity D. Activity D is…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a). Develop a project network. (b) Develop an activity schedule. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F (c) What are the critical activities? (Enter your answers as…