3. A company which produces a single product has definite orders for this product over the next six months as follows: 1 3 4 5 Month 2 Demand 350 680 475 590 460 6 390 The company ended the previous month (month 0) with an inventory of 200 units, and the previous month production level was 400 units. The company wishes to end this six-month planning period with an inventory of at least 50 units. It costs $3.50 per unit to increase the production level from one month to the next, and $6.00 per unit to decrease it. The cost of holding inventory from one month to the next is $4.80 per unit per month. No shortages are permitted. In each month, the company wants to produce an integer number of units. The company wishes to minimize the sum of production level change costs and inventory costs over the six-month planning horizon.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 33P: Assume the demand for a companys drug Wozac during the current year is 50,000, and assume demand...
icon
Related questions
Question
3. A company which produces a single product has definite orders for this product
over the next six months as follows:
1
2
3
4
5
6
Month
Demand 350 680 475 590 460 390
The company ended the previous month (month 0) with an inventory of 200 units,
and the previous month production level was 400 units. The company wishes to
end this six-month planning period with an inventory of at least 50 units.
It costs $3.50 per unit to increase the production level from one month to the next,
and $6.00 per unit to decrease it. The cost of holding inventory from one month to
the next is $4.80 per unit per month. No shortages are permitted. In each month.
the company wants to produce an integer number of units. The company wishes
to minimize the sum of production level change costs and inventory costs over the
six-month planning horizon.
Transcribed Image Text:3. A company which produces a single product has definite orders for this product over the next six months as follows: 1 2 3 4 5 6 Month Demand 350 680 475 590 460 390 The company ended the previous month (month 0) with an inventory of 200 units, and the previous month production level was 400 units. The company wishes to end this six-month planning period with an inventory of at least 50 units. It costs $3.50 per unit to increase the production level from one month to the next, and $6.00 per unit to decrease it. The cost of holding inventory from one month to the next is $4.80 per unit per month. No shortages are permitted. In each month. the company wants to produce an integer number of units. The company wishes to minimize the sum of production level change costs and inventory costs over the six-month planning horizon.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Merchandise Inventory
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS