1. Form reduced system cost pools for activities 7 and 8. Do not round interim calculations. Round your final answers to the nearest dollar. Inserting dies cost pool Purchasing cost pool 2. Assign the costs of the reduced system cost pools to Wafer A and Wafer B. Do not round interim calculations. Round your final answers to the nearest dollar. Wafer A Wafer B X 3. What if the two activities were 1 and 3? Repeat Requirements 1 and 2.

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter4: Activity-based Costing
Section: Chapter Questions
Problem 10CE: Selected activities and other information are provided for Patterson Company for its most recent...
icon
Related questions
Question
Simplifying the ABC System: Equally Accurate Reduced ABC Systems
Selected activities and other information are provided for Patterson Company for its most recent year of operations.
Expected Consumption
Activity
7. Inserting dies
8. Purchasing materials
1. Developing test programs
3. Testing products
ABC assignments
Total overhead cost
Required:
Driver
Number of dies
Number of purchase
orders
Engineering hours
Test hours
Wafer A
Wafer B
Quantity
1,900,000
X
والے
1,900
9,000
19,000
3. What if the two activities were 1 and 3? Repeat Requirements 1 and 2.
Wafer A
0.7
0.2
Ratios
0.25
0.6
$165,000
1. Form reduced system cost pools for activities 7 and 8. Do not round interim calculations. Round your final answers to the nearest dollar.
Inserting dies cost pool
Purchasing cost pool
Wafer B
0.3
2. As the costs of the reduced system cost pools to Wafer A and Wafer B. Do not round interim calculations. Round your final answers to the nearest dollar.
0.8
0.75
0.4
$165,000
$330,000
Transcribed Image Text:Simplifying the ABC System: Equally Accurate Reduced ABC Systems Selected activities and other information are provided for Patterson Company for its most recent year of operations. Expected Consumption Activity 7. Inserting dies 8. Purchasing materials 1. Developing test programs 3. Testing products ABC assignments Total overhead cost Required: Driver Number of dies Number of purchase orders Engineering hours Test hours Wafer A Wafer B Quantity 1,900,000 X والے 1,900 9,000 19,000 3. What if the two activities were 1 and 3? Repeat Requirements 1 and 2. Wafer A 0.7 0.2 Ratios 0.25 0.6 $165,000 1. Form reduced system cost pools for activities 7 and 8. Do not round interim calculations. Round your final answers to the nearest dollar. Inserting dies cost pool Purchasing cost pool Wafer B 0.3 2. As the costs of the reduced system cost pools to Wafer A and Wafer B. Do not round interim calculations. Round your final answers to the nearest dollar. 0.8 0.75 0.4 $165,000 $330,000
Expert Solution
steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Cost estimation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning