Using the activity list below and any appropriate drawing tool, create a complete network diagram using the precedence method showing Activity, Duration, ES, EF, LS, LF and Slack per activity: ACTIVITY A BU C D EF G H DURATION 5 12 20 15 15 30 12 8 00 PREDECESSOR A B B B C, D E, F G

Residential Construction Academy: House Wiring (MindTap Course List)
4th Edition
ISBN:9781285852225
Author:Gregory W Fletcher
Publisher:Gregory W Fletcher
Chapter1: Residential Workplace Safety
Section: Chapter Questions
Problem 27RQ
icon
Related questions
Question
Using the activity list below and any appropriate drawing tool, create a complete network diagram
using the precedence method showing Activity, Duration, ES, EF, LS, LF and Slack per activity:
ACTIVITY
A
B
C
D
E
F
G
H
DURATION
5
12
20
15
15
30
12
8
PREDECESSOR
A
B
B
B
C, D
E, F
G
Transcribed Image Text:Using the activity list below and any appropriate drawing tool, create a complete network diagram using the precedence method showing Activity, Duration, ES, EF, LS, LF and Slack per activity: ACTIVITY A B C D E F G H DURATION 5 12 20 15 15 30 12 8 PREDECESSOR A B B B C, D E, F G
Expert Solution
steps

Step by step

Solved in 6 steps with 7 images

Blurred answer
Knowledge Booster
Types of Scheduling Techniques
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Residential Construction Academy: House Wiring (M…
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning
Architectural Drafting and Design (MindTap Course…
Architectural Drafting and Design (MindTap Course…
Civil Engineering
ISBN:
9781285165738
Author:
Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:
Cengage Learning