The answers of a-d already existed still need to find the other questions   Question A company has a 12% WACC and is considering two mutually exclusive investments (that cannot be repeated) with the following cash flows:   Project A -$300 -$387 -$193 -$100 $600 $600 $850 -$180 Project B -$400 $135 $135 $135 $135 $135 $135 $0 a. What is each project's NPV? project A :$200.41 project B :$155.04 b. What is each project's IRR? project A :18.10% project B :24.83% c. What is each project's MIRR? project A :15.1% project B :17.4%   d. From your answers to Parts a, b, and c, which project would be selected? If the WACC was 18%, which project would be selected? Already answered e. Construct NPV profiles for Projects A and B discount rate NPV PLAN B. NPV PLAN B Discount Rate NPV Project A NPV Project B 0% $   $ 5     10     12     15     18.1     24.83     Formula: f. Calculate the crossover rate where the two projects' NPVs are equal. Formula: g. What is each project's MIRR at a WACC of 18% Formula:

Intermediate Financial Management (MindTap Course List)
13th Edition
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Eugene F. Brigham, Phillip R. Daves
Chapter12: Capital Budgeting: Decision Criteria
Section: Chapter Questions
Problem 13P
icon
Related questions
Question
The answers of a-d already existed still need to find the other questions
 
Question
A company has a 12% WACC and is considering two mutually exclusive investments (that cannot be repeated) with the following cash flows:

 

Project A -$300 -$387 -$193 -$100 $600 $600 $850 -$180
Project B -$400 $135 $135 $135 $135 $135 $135 $0



a. What is each project's NPV?
project A :$200.41
project B :$155.04

b. What is each project's IRR?
project A :18.10%
project B :24.83%

c. What is each project's MIRR?
project A :15.1%
project B :17.4%

 


d. From your answers to Parts a, b, and c, which project would be selected?
If the WACC was 18%, which project would be selected? Already answered


e. Construct NPV profiles for Projects A and B
discount rate NPV PLAN B. NPV PLAN B

Discount Rate NPV Project A NPV Project B
0% $   $
5    
10    
12    
15    
18.1    
24.83    


Formula:

f. Calculate the crossover rate where the two projects' NPVs are equal.
Formula:

g. What is each project's MIRR at a WACC of 18%

Formula:

Expert Solution
steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Knowledge Booster
New Line profitability analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning