9. The following six activities constitute an overall bar chart portrayal of a 4-month project. Two months after the start of construction, Activities A, C, D, half of E, and one-fourth of B were completed, for a cost of $10,500. Evaluate the status of the project. Using earned value concepts, determine the schedule variance and the cost variance. State if the project is over or under budget and if it is ahead of or behind schedule.and their percentages and PC. Activity A B C D E F Cost $2,000 $8,000 $2.000 $5,000 $1.000 $15,000 Month Month 2 Month 3 Month 4

Holt Mcdougal Larson Pre-algebra: Student Edition 2012
1st Edition
ISBN:9780547587776
Author:HOLT MCDOUGAL
Publisher:HOLT MCDOUGAL
ChapterCSR: Contents Of Student Resources
Section: Chapter Questions
Problem 7.30EP
icon
Related questions
Question
Alert for not submit AI generated answer. I need unique and correct answer. Don't try to copy from anywhere. Do not give answer in image formet and hand writing
9. The following six activities constitute an overall bar chart portrayal of a 4-month project.
Two months after the start of construction, Activities A, C, D, half of E, and one-fourth of B were completed, for a cost of
$10,500. Evaluate the status of the project. Using earned value concepts, determine the schedule variance and the cost
variance. State if the project is over or under budget and if it is ahead of or behind schedule.and their percentages and PC.
Activity Cost
A
B
C
D
E
F
$2,000
$8,000
$2,000
$5,000
$1.000
$15,000
Month
1
Month
2
Month
3
Month
4
Transcribed Image Text:9. The following six activities constitute an overall bar chart portrayal of a 4-month project. Two months after the start of construction, Activities A, C, D, half of E, and one-fourth of B were completed, for a cost of $10,500. Evaluate the status of the project. Using earned value concepts, determine the schedule variance and the cost variance. State if the project is over or under budget and if it is ahead of or behind schedule.and their percentages and PC. Activity Cost A B C D E F $2,000 $8,000 $2,000 $5,000 $1.000 $15,000 Month 1 Month 2 Month 3 Month 4
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Similar questions
Recommended textbooks for you
Holt Mcdougal Larson Pre-algebra: Student Edition…
Holt Mcdougal Larson Pre-algebra: Student Edition…
Algebra
ISBN:
9780547587776
Author:
HOLT MCDOUGAL
Publisher:
HOLT MCDOUGAL